An efficient progress management approach by subjective maturity using check list

ln this report, we describe an efFicient method of work progress management using an olljective maturity based on check list.
ln recent busmess activities of development project in industrial area and so fbrth, Work progress reports which are submitted
by engineer depend on senses of engineer. This situation causes a problem that project manager can hardly recognize actual
progress. Theref1)re we propose a new emcient method to use not only sulljective value input by engineer but also objective
value which is predicted using accumulated check list values.

By: Hirofumi Matsuzawa, Atsushi Fukuda, Takashi Nerome

Published in: RT5299 in 2009

LIMITED DISTRIBUTION NOTICE:

This Research Report is available. This report has been submitted for publication outside of IBM and will probably be copyrighted if accepted for publication. It has been issued as a Research Report for early dissemination of its contents. In view of the transfer of copyright to the outside publisher, its distribution outside of IBM prior to publication should be limited to peer communications and specific requests. After outside publication, requests should be filled only by reprints or legally obtained copies of the article (e.g., payment of royalties). I have read and understand this notice and am a member of the scientific community outside or inside of IBM seeking a single copy only.